Service High School Renewal Continues
June 13, 2014
With students and teachers on summer break, Cornerstone has been able to intensify its effort at Service High School.
Most recently, the existing generator and housekeeping pad has been demolished and new generator preparations made. Mechanical, electrical, and plumbing work has been expanded in various areas and between buildings.
Significant demolition and abatement activities may be seen in the library (seen in photo), where the concrete floor slab and rebar, stairs, columns, and support members of the old central mezzanine were removed.